Proposed Sanitary Sewer No. 3976

CIP 2001-26

DEER PARK/MATSON AVENUE RELIEF SEWER

 

DETAILED PROVISIONS

 

 

SOIL BORINGS

 

Test borings that were drilled for this project have been indicated on the plans.  Prospective Bidders are hereby notified that a copy of the test borings are available at the Plans Sales Desk, Room 100, Department of Sewers, Division of Wastewater Engineering, 1600 Gest Street, Cincinnati, Ohio 45204, upon execution of a "Test Boring Information Waiver of Liability".

 

The geotechnical report was not prepared for purposes of bid development and the accuracy of the report is limited. The Contractor should confer with a geotechnical engineer and/or conduct additional study, in the area, to obtain specific type of geotechnical information required for construction and for preparation of bids. The Contractor should not over rely on the construction recommendations included in the report.  These recommendations in the report are not final and are developed principally from the judgment and opinion of the geotechnical engineer who prepared the report.

 

Rock cores are available for viewing upon request in Room 101, Department of Sewers, Division of Wastewater Engineering, 1600 Gest Street.

 

 

CONSTRUCTION SEQUENCE

 

Before construction is started, the Contractor shall submit a construction schedule to the Engineer. This schedule shall outline the sequence in which the Contractor proposes to conduct operations and shall be approved by Engineer before work is started. It shall be the responsibility of the Contractor to uncover the existing conduit as the first order of work in order to determine the elevation and alignment of the exiting conduit. The Engineer shall determine if adjustments are required. The schedule shall include calendar dates of start and completion of each task of the work. The Contractor should consider the following constraints in preparation of the construction schedule:

 

  1. Develop vehicular and pedestrian traffic control plan including detours, closures, barricades, signage and related traffic maintenance requirements. Maintain work zone traffic accordance with item 614 of the Ohio Department of Transportation (ODOT) Construction and Material Specifications (CMS) and the City of Cincinnati Supplement 2002 (City Supplement) unless otherwise indicated. Additional work zone traffic maintenance requirements are provided on Sheet 3.
  2. Establish construction staging and parking areas. Limit construction access to designated routes to minimize disruption of local traffic.
  3. Temporary pumping and ancillary equipment for maintenance of flow, including temporary power.
  4. Dust, noise sediment and erosion control systems.
  5. Saw cut pavement and remove as required for daily construction.
  6. Construct relief sewer including sheeting/bracing, dewatering, groundwater control, excavation, bedding, lateral connections, manholes, sewer connections, initial backfill, final backfill and temporary surface at Type B sewers.
  7. Daily cleanup and maintenance of project area.
  8. Test sewers and appurtenances. Replace defective items and retest if necessary.
  9. Final paving at Type B sewers.
  10. Final cleanup of project including construction staging and parking areas.
  11. Record Drawings for close-out.

 

Construction Constraints that should be considered prior to bidding include but are not limited to the following:

 

  1. Rock excavation
  2. Groundwater control
  3. Deep excavations (over 20-feet deep)
  4. Tunneling under storm sewers
  5. Establishment of construction staging and worker/equipment parking areas. If the Contractor finds it necessary to obtain additional working area, it shall be the responsibility of the Contractor to acquire it at no additional cost to the Owner.
  6. Temporary pumping and ancillary equipment as necessary for maintenance of sewer flow, including temporary power for the same.
  7. Control measures for dust, noise, and sediment/erosion.
  8. Ancillary work related to relief sewer construction including, but not limited to:

 

In accordance with 108.06 of the ODOT,  Construction and Material Specifications (CMS), and the City Supplement, the Contractor shall plan and prosecute the work for completion and final acceptance by the date for completion stated in the proposal.

 

Whenever it becomes apparent from the current monthly progress evaluation and updated schedule data that any milestone and/or date for completion will not be met, the respective Contractor shall take some or all of the following actions:

 

  1. Increase construction manpower in such quantities and crafts as shall subsequently eliminate the backlog of work.
  2. Increase the number of working hours per shift, shifts per week, work days per week, or the amount of construction equipment, or any combination of the foregoing sufficient to substantially eliminate the backlog of work.
  3. Reschedule work items to achieve concurrence of accomplishment.

 

In addition of equipment or construction forces, increasing the working hours or any other method, manner or procedure to return to the current Detailed Schedule shall be at the respective Contractor’s own cost and shall not be considered justification for a Change Order or treated as an acceleration order.

 

 

LIQUIDATED DAMAGES

                       

Per the requirements of Section lll.F, “Binding Effect”, of the “Interim Partial Consent Decree for Sanitary Sewer Overflows”, the Metropolitan Sewer District of Greater Cincinnati (MSD) hereby notifies the Contractor of the following:

 

On February 15, 2002, the United States EPA, United States Department of Justice, and the State of Ohio lodged with the United States District Court for the Southern District of Ohio Western Division, an “Interim Partial Consent Decree for Sanitary Sewer Overflows”.  Copies of the Consent Decree are available from the Metropolitan Sewer District of Greater Cincinnati, Regulatory Response Unit, 1600 Gest Street, Cincinnati, OH 45204. 

 

Liquidated damages per 109.12 of the City of Cincinnati Supplement shall be assessed to the Contractor for failure to complete construction by the end of April 30, 2005. Beginning May 1, 2005, the assessments will be applied, as follows, until construction is complete:

 

            1   - 30 days                 $1,500/day

            31 - 60 days                 $3,000/day

            Over 60 days               $5,000/day      

 

 

GENERAL PROVISIONS

 

The work shall be in accordance with the requirements to the General Provisions of the City of Cincinnati Supplement, 2002 edition.

 

 

SAFETY ADVISORY

 

A.  Scope: Sanitary Sewer Construction

 

B.   The Contractor shall at all times conduct the work safely in order to assure a safe work site. The Contractor shall be responsible for the safety of the Contractor’s employees, agents and subcontractors, City personnel and all other personnel or persons at the work site. The Contractor shall be responsible for the adequacy and safety of all construction methods or procedures and the safe prosecution of the work.

 

C.  The Contractor shall be responsible at all times to conduct the work and keep the work site in compliance with federal, state and local safety laws and regulations, including but not limited to Occupational Safety and health Administration (OSHA) requirements.

 

D.  The Contractor shall be responsible to suspend work whenever a work method or procedure or a condition at a work site is unsafe.

 

E.   The Contractor shall submit a written notification to the City of any accident or injury. The Contractor shall also send written notification of all accidents and injuries to the Employee Safety Division. Such notification shall include the Contractor’s investigation and what measures are appropriate to avoid such accidents. Payment applications will not be authorized until such notice is provided.

 

F.   The Contractor will conduct Site Safety Audits on a periodic basis, to be determined by the MSD Project Engineer. The audit shall be performed using the Audit Checklist incorporated in the City Supplement. The Contractor’s safety representative will perform the audit with the City’s authorized representative in attendance. A copy of the completed Audit Checklist shall be furnished to the City.

 

G.  None of the provisions of this section are intended to nor shall be construed to create any duty or responsibility on the City to provide or enforce safety requirements for the Contractor. The duty, responsibility and liability for safety, shall remain with the Contractor.

 

 

REFERENCES

 

  1. Conform to reference standards by date of issue that are current on the date of Contract Documents.

 

B.   Should specified reference standards conflict with Contract Documents, request clarification from the City or the City’s Authorized Representative before proceeding.

C.  The contractual relationship of the parties to the Contract shall not be altered from the Contract Documents by mention or inference otherwise in any reference document.

 

D.  Comply with all applicable requirements of the Occupational Safety and Health Administration (OSHA).

 

E.   Conform to all applicable requirements of the City of Cincinnati Supplemental sections 107.07, and 107.071, issued as an amendment to Ohio Department of Transportation (ODOT) regulations.

 

 

JOB SPECIFIC PRECAUTIONS

 

A.  The Contractor is advised to consider the job specific elements of the work when preparing and executing the safety plan.

 

B.   The Contractor shall make his own site investigation and evaluation for job or site-specific safety concerns in addition to those listed herein.

 

C.  The following should be considered in preparation of the safety plan specific to the work governed by this contract. The list does not limit, evaluate or influence the means and methods of construction.

 

1.     MAINTAINING SAFETY IN WORK ZONE.

2.         PROTECTION OF PEDESTRIANS (barricades, signs, sidewalk closures & temporary walkways).

3.         TRAFFIC MAINTENANCE.

4.         CONSTRUCTION PARKING AND ACCESS.

5.         STORAGE OF EQUIPMENT AND MATERIALS.

6.         DUST CONTROL.

7.         WORKING IN TRENCHES (OSHA soil classification, groundwater & utility crossings).

8.         MOVING AND LIFTING OF PIPING MATERIALS.

9.         CONFINED SPACE ENTRY (manholes & sewer connections).

10.     FIRST AID.

11.     ELECTRICAL (temporary power & extension cords).

12.     SANITATION.

13.     FIRE PROTECTION.

14.     TEMPORARY PUMPING.

15.     “HOT WORK PERMIT” (obtain before use of sparking or open flame equipment).

 

THE ABOVE LIST IS NOT INTENDED TO BE AN ALL-INCLUSIVE LIST AND THE CONTRACTOR IS RESPONSIBLE FOR SAFETY IN ALL AREAS WHETHER LISTED ABOVE OR NOT.

 

PRECONSTRUCTION MEETING

 

Following award of the Contract and before starting any work, the Contractor, the Contractor’s Superintendent, and Foreman shall meet with the Engineer, the Field Engineer and the Inspector in the office of the Engineer for a preconstruction meeting.  The Contractor will be notified of the date and the time of the meeting.

 

 

MAINTENANCE OF TRAFFIC

 

The Contractor shall be responsible for maintaining “local” traffic at all times and for notifying the proper authorities regarding the closing of roads.

 

It is the intention to perform the required work with the least inconvenience to, and maximum safety of the Contractor and the traveling public.  The Engineer must approve any variances from these Maintenance of Traffic notes in advance, in writing.

 

The Contractor shall not begin work until standard barricades and warning signs are in acceptable position and the markers and signs conform to the "Ohio Manual of Uniform Traffic Control Devices for Streets and Highways". The cost of all traffic control devices shall be included in the various contract items.

 

The Contractor shall maintain local traffic at all times during construction of this project in a manner causing the least amount of inconvenience to the abutting property owners.  Temporary Driveways, Temporary Roadways, or Turn-Arounds as may be necessary to provide vehicular access to and from the abutting properties shall be constructed, maintained and subsequently removed by the Contractor, as directed by the Engineer.

 

MSD will obtain, process and pay for all required street opening permits.  Any cost for inspection and testing required by jurisdictional agencies, in addition to that supplied as part of the street opening permit, will be billed to and paid by MSD, excluding penalty charges for delays due to the Contractor's operations.

 

When excavating in the street pavement, the portion of the street pavement not in the sewer main construction shall be kept clear of all excavated material.  Only a portion of the trench shall be excavated at a time and closed again with bank run gravel, before the pavement over the balance is removed, as directed by the Engineer.

 

All pavement and/or right‑of‑way openings within the public right‑of‑way must conform to the current edition of the State of Ohio, Department of Transportation, Construction and Material Specifications, with supplements or changes thereto.  Also, the Contractor assumes all responsibilities and liabilities regarding strict adherence to applicable sections for the Maintenance of Traffic and Public Safety as set forth in the "Ohio Manual of Uniform Traffic Control Devices for Streets and Highways".  All traffic control devices must be in place prior to starting construction.

 

The Contractor shall save harmless the City of Deer Park, City of Cincinnati and the Board of County Commissioners of Hamilton County and all its representation from all suits, actions, or claims of any character brought on account of any injuries or damages sustained by any person, or persons, or property in consequence of this construction project due to construction operations.

 

Police, Fire and School Bus access shall be maintained at all times.  If at any time traffic has to be blocked, the Contractor shall notify the City of Deer Park, local Police District, Fire Division and School District Transportation Office.

 

Work along E. Galbraith Road from Gwilada Drive to Gail Avenue and along Plainfield Road from Matson Avenue to Schenck Avenue shall be between the hours of 9:00 a.m. and 4:00 p.m.

 

The cost of the maintenance of traffic shall be included in the various contract items.

 

 

EXISTING UTILITIES

 

The Contract Drawings show all underground utilities, water, gas, and sewer lines known to exist. However, this does not guarantee that all existing lines and appurtenances have been shown on the Contract Drawings, and the City of Deer Park, City of Cincinnati and MSD assume no responsibility for the accuracy thereof and do not free the Contractor from necessary precautions for the protection of any utility encountered on the project or the restoration of any utility damaged during the work. It shall be the responsibility of the Contractor to uncover the existing utilities as the first order of work in order to determine their elevation and alignment.

 

The Contractor shall notify, at least 48 hours before breaking ground, all public and/or private service corporations having wire, poles, pipes, conduit, manholes or other structures that may be affected by this operation, including all structures which are affected and not shown on the Contract Drawings.  Owners of underground utilities, which are members of the Ohio Utilities Protection Service, can be notified by calling 800‑362‑2764 (toll free).  Non‑member underground utility owners must be called directly.

 

Supporting and/or protecting existing water lines, gas mains, telephone conduit, guy lines, electric/telephone poles, storm sewers, etc., shall be included in payment for the various contract items of work.

 

All work required for the maintenance of service of existing utilities shall be done by, and at the expense of the Contractor.

 

All maintenance, repair and/or replacement of existing utilities shall be in accordance with the Rules and Regulations of the various utility companies having jurisdiction.

 

All existing storm sewers, driveway drains, and other surface drain pipes, whether shown on the Contract Drawings or not, removed or damaged during construction shall be repaired and reconnected by the Contractor, as directed by the Engineer, at no cost to the City.

 

It is assumed that there are water and gas branch lines, etc., serving each residence.  The Contractor shall repair or replace these utilities, if damaged, at no cost to the City.

 

 

CONSTRUCTION PROCEDURE

 

It shall be the Contractor's responsibility during the construction of this project to work equipment around poles, trees, or other obstructions which permit the passage of the bucket and boom but prevent passage of other portions of the equipment and, if necessary, to excavate from both sides of the poles, trees, or other obstruction, and to remove materials by hand labor, tunneling, or by other means, all at the Contractor’s own expense.

 

It is the intent of these Detailed Provisions to provide a procedure for keeping the restoration of seed and sod areas and driveways current with the installation of the sewer pipe.  This will be considered a part of the sewer installation and failure to keep restoration of these items completed reasonably close to the installation of the sewer pipe shall be cause to delay payment for sewer pipe installed until such restoration is completed to the satisfaction of the Engineer.

 

 

REQUEST FOR SUPPLEMENTARY INFORMATION

 

It shall be the responsibility of the Contractor to make timely requests of the City for any additional information not already in the Contractor’s possession and which should be furnished by the City under the terms of this Contract, and which will be required in the planning and execution of the work.  Such requests may be submitted from time to time as the need approaches, but each shall be filed in ample time to permit appropriate action to be taken by all parties involved so as to avoid delay.

Each request shall be in writing, and list the various items and the latest day by which each will be required by the Contractor.  The first list shall be submitted within two (2) weeks after contract award and shall be as complete as possible at that time.  The Contractor shall, if required, furnish promptly any assistance and information the Engineer may require in responding to these requests of the Contractor.  The Contractor shall be fully responsible for any delay in work, or to the work of others, arising from failure to comply with the provisions of this section.

 

 

USE OF PREMISES

 

The Contractor shall not trespass upon or in any way disturb property outside the street right‑of‑way, or outside the limits of construction, without first obtaining written permission from the owner to do so.  A copy of such written permission shall be furnished to the Engineer.

 

If the Contractor finds it necessary to obtain additional working area, it shall be the Contractor’s responsibility for its acquisition.  All requirements listed under the "Use of Premises" shall apply if additional area is obtained.

 

The Contractor shall, at the Contractor’s expense, restore such property to the full satisfaction of the owner, and shall obtain from the owner a written release stating that restoration has been satisfactorily made.  A copy of the written release shall be furnished to the Engineer.

 

The Contractor shall not waste any excess earth, stone, or other excavated material on any property without first obtaining written permission from the owner of the property and securing the approval of the Engineer.  One copy of the owner's written permission, and one copy of a written release from the owner stating that the work has been completed satisfactorily, shall be furnished to the Engineer.

 

All items within the construction limits and the street right‑of‑way shall be removed, or removed and replaced, or restored as required by the Contract Drawings and Specifications, as directed by the Engineer.

 

 

PROTECTION OF TREES

 

The Contractor shall take precautions to avoid any unnecessary damage to trees.  Branches which overhang the construction limits and which interfere with the operation of equipment shall be tied back to avoid damage, if possible.  Where injury to branches is unavoidable, the branches shall be sawed off neatly at the trunk or main branch and the cut area shall be painted with an approved tree paint immediately.  Any trees damaged beyond saving shall be removed by the Contractor at the Contractor’s expense, and in the case of trees located on private property, the Contractor shall make restitution to the owner.

 

 

MAINTAINING FLOW

 

It will be the responsibility of the Contractor, throughout the tenure of this contract, to provide and maintain sufficient flow at all times to pass any flash or storm flow of drainage ditches, creeks, streams and rivers, and to prevent any backwater flooding due to obstruction caused by construction equipment and/or materials.

 

The Contractor shall maintain sewage flow of the sewer main at all times during construction of the proposed conduit by by-pass pumping or diverting sewage flow into temporarily installed conduit.  The pumps or conduit used to maintain flow must be of adequate size to prevent surcharging of the existing sewer.  This cost shall be included with the various 603 items.

 

The Contractor shall be responsible for prohibiting storm or subsurface water from entering the sanitary sewer during construction as may be caused by flash floods, heavy rains, etc.

 

The cost of this work shall be included in the unit price bid for the various contract items.

 

 

FENCING, SIGNS, MAILBOXES, AND GUARDRAILS

 

Any fences, signs, mailboxes, and guardrails that need to be removed to facilitate sewer construction operations shall be replaced, in kind or with repairs satisfactory to the owner, at the Contractor's expense.  Replacement of fences, signs, mailboxes and guardrails shall be considered a part of the sewer installation and shall be done immediately after the installation and backfilling of the sewer.  The costs for the removal and replacement shall be included in the price bid for the various contract items.

 

 

RESTORATION

 

All restoration shall be completed in strict accordance with the appropriate items of the Specifications, as directed by the Engineer.

 

The cost of all restoration of streets, drives, walks, sod, etc., shall be included in the various items of the Contract.  When restoring walks, curb ramps shall be constructed at intersections where the existing walk has been disturbed.  Contact the jurisdictional agency for curb ramp requirements.

 

All drainage ditches disturbed by the Contractor’s work shall be restored, reshaped and graded to drain properly.

 

All disturbed areas shall be restored as nearly as practical to the condition they were prior to construction.

 

Pavement restoration shall be in accordance with the “Typical Restoration Section” and the provisions of the Governing Agency responsible for the particular road, as directed by the Engineer.

 

The restoration of sunken trenches shall be the Contractor's responsibility.  Sunken areas shall be backfilled and compacted to meet adjoining grades and the surface area reseeded, or resurfaced with asphalt or concrete matching the existing surfacing.  The Contractor's responsibility for this item shall be under the terms of, and for the duration of, the guarantee defined in 109.12 of the City Supplement.

 

The Contractor shall restore unpaved areas by seeding and mulching (Item 659) unless otherwise noted herein.  Commercial fertilizer shall be used and shall have a chemical analysis of 12‑12‑12.  The fertilizer shall be delivered to the project site in manufacturer's containers, unopened.  The container, or an attached tag, shall have printed upon it the manufacturer's name and the chemical analysis of the contents.

 

Driveways shall be restored in kind or with two (2) inches of Asphalt Surface Course (Item 448) on a six (6) inch Aggregate Base (Item 304) or with seven (7) inch thick Plain Non-Reinforced Concrete Pavement Portland Cement Concrete Pavement (Item 452).  Concrete walks shall be restored with a five (5) inch thick Plain Portland Cement Concrete Walk (Item 608).

 

 

202 (Ref. No. 1) FILL, SEAL AND ABANDON EXISTING SEWERS

 

This item shall be constructed as shown on the plans and as directed by the Engineer.  Fill, seal and abandon the existing 15” sewer in accordance with the method described in section 202.041 of the Cincinnati Supplement to the State of Ohio, Department of Transportation, Construction and Material Specification.

 

This item will be used in other areas only when directed by the Engineer.  Payment will be based on the unit price bid per cubic yard.

 

 

202 (Ref. No. 2) SEAL AND ABANDON EXISTING SEWERS

 

Sewers that are to be abandoned shall be plugged or sealed where they join manholes, catch basins, or inlets.  All existing sewers encountered in construction operations that are inactive, or are to be abandoned as determined by the Engineer, shall be plugged or sealed at both ends where broken into, before proceeding with backfilling.

 

Where plugging or sealing is required, pipe 12-inches or less in diameter shall be sealed by the installation of a suitable precast concrete or vitrified clay stopper, properly cemented into place. Pipe or masonry sewers larger than 12-inches in diameter shall be sealed at the required locations by the construction of a masonry bulkhead of brick, stone, or concrete having a thickness of one-half of the sewer diameter, except that the minimum thickness shall be 12-inches and the maximum thickness shall be 24-inches.

 

 

202 (Ref. No. 3) MANHOLES ABANDONED

 

Manholes shall be abandoned in accordance with Item 202.11 of the State of Ohio (ODOT) Construction and Material Specifications.  All castings shall be disposed of at the Contractor’s expense.  This item shall include all sanitary manholes to be abandoned as shown on the plans or as directed by the Engineer.

 

 

 

 

204 (Ref. No. 4) SPECIAL EXCAVATION

 

This is a contingency item.

 

This item will be used only when directed by the Engineer.

 

 

205 (Ref. No. 5) SPECIAL FILL MATERIAL (BANK RUN GRAVEL)

 

This is a contingency item.

 

Only special fill material not included in other pay items shall be measured for payment.

 

 

205 (Ref. No. 6) SPECIAL FILL MATERIAL (No. 3 GRAVEL BEDDING)

 

This is a contingency item.

 

The Contractor, only as directed by the Engineer, when this particular type of material is required in the work, shall furnish No. 3 Gravel Bedding meeting the requirements of Item 703.11 of the State of Ohio (ODOT) Construction and Material Specifications. 

 

 

602 (Ref. No. 7) CONCRETE MASONRY, CLASS "C"

 

This is a contingency item.

 

Only special Class "C" Concrete Masonry not included in other pay items shall be measured for payment, as directed by the Engineer.

 

 

602 (Ref. No. 8) CONCRETE MASONRY, CLASS “C” (ENCASEMENT, CRADLES, KEY BLOCKS AND COLLARS)

 

This is a contingency item.

 

Only special Class “C” concrete masonry used for encasement, cradles, key blocks and collars, in addition to those items called for in the plans, shall be measured for payment, as directed by the Engineer.

 

 

603 (Ref. Nos. 9 through 18) CONDUITS, STUBS, AND T-BRANCHES

 

All backfill operations required under these items shall be in accordance with the City of Cincinnati Supplement to the State of Ohio (ODOT) Construction and Material Specifications, Item 603.017, except as otherwise noted herein.  All requirements of these items shall be strictly adhered to by the Contractor and enforced by the Department of Sewers.

 

The price bid for these items shall be complete, and shall include all necessary clearing; excavation; embankment; dewatering; maintaining existing sanitary flow; sheeting; preparation of trench bottom; granular bedding and initial backfill; pipe; joint material; backfill; testing; disposal of waste material; dust, odor and noise control; traffic control; lights, signs and barricades; cleaning up; saw cutting; and concrete encasement.

 

Stub lengths shall be included and paid per foot of conduit specified. 

 

Partial payments for these items shall be paid by the Metropolitan Sewer District in accordance with the following schedule:

 

Eighty-five percent (85%) of the unit price bid for Jacking and Boring shall be paid for pipe installed as per plans.

 

Eighty percent (80%) of the unit price bid for Type “C” and Type “G” Conduit shall be paid for pipe installed, including initial backfill.

 

Seventy percent (70%) of the unit price bid for Type “B” Conduit shall be paid for pipe installed, including initial backfill.

 

An additional ten percent (10%) of the unit price bid for Jacking and Boring, Type “B”, Type “C”, and Type “G” Conduit shall be paid when the pipe passes the leakage test, and also the deflection test when PVC pipe is installed.

 

The remaining portion of the unit price bid shall be paid when video taping of the installed sewers and final restoration has been completed. Final restoration is defined as when seeding/mulching is in place in unpaved areas, and when pavement/roadway work is complete in paved areas.

 

Whenever the proposed sewer is located at approximately the same alignment as the existing sewer and it is necessary to remove the existing sewer in order to construct the proposed sewer, the cost for removing the existing sewer, including the cost for disposing and transporting of materials or any additional excavation, restoration, or labor required, shall be included in the price bid for the various 603 items.

 

It shall be the responsibility of the Contractor to uncover the existing sewer as the first order of work in order to determine the elevation and alignment of the existing conduit.  The Engineer shall determine if adjustments are required.

 

If PVC (S.D.R. 35) Pipe is used under these items, all operations shall be in accordance with Items 603.016 and 707.41 of the City of Cincinnati Supplement to the State of Ohio, Department of Transportation, Construction and Material Specifications, latest edition.  PVC sewer pipe and fittings, ASTM D-3034 and ASTM F-679 (ASTM F-679 for 18” and greater PVC only) latest edition, shall have ASTM D-3212 joints (flexible elastomeric seals).

 

“Blue Brute – PVC C-900”, Polyvinyl Chloride Pressure Pipe, shall conform to the requirements of AWWA C-900 Specifications.  Joints for PVC C-900 pipe and fittings shall conform to AWWA C-111 Specifications.

 

“Ultra-Rib” PVC Pipe, as manufactured by Extrusion Technologies, Inc., shall meet the performance requirements of ASTM F794 “Standard Specification for Poly (Vinyl Chloride) (PVC) Profile Gravity Sewer Pipe and Fittings Based on Controlled Inside Diameter”.  Flexible elastomeric seals meeting the requirements of ASTM D-3212 shall be used with “Ultra-Rib” PVC Pipe.

 

“Vylon” PVC Pipe, as manufactured by Lamson Co., shall meet the performance requirements of ASTM F1803 “Standard Specification for Poly (Vinyl Chloride) (PVC) Closed Profile Gravity Pipe and Fittings Based on Controlled Inside Diameter”.  Flexible elastomeric seals meeting the requirements of ASTM D-3212 shall be used with “Vylon”  PVC Pipe.  When this pipe material is proposed to be utilized for Conduit in Tunnel or Jack & Bore, the cost of the pipe shall be included in the price bid for the contract item.

 

“A-2000” PVC Pipe, as manufactured by Contech Construction Products, Inc., shall meet the performance requirements of ASTM F949 “Standard Specification for Poly (Vinyl Chloride) (PVC) Corrugated Sewer Pipe with a Smooth Interior and Fittings”.  Flexible elastomeric seals meeting the requirements of ASTM D-3212 shall be used with “A-2000” PVC Pipe.

 

Carlon PVC Pipe”, PS 46, shall meet the performance requirements of ASTM F789 “Standard Specification for Type PS-46 and Type PS-115 Poly (Vinyl Chloride) (PVC) Plastic Gravity Flow Sewer Pipe and Fittings”.  Flexible elastomeric seals meeting the requirements of ASTM D-3212 shall be used with “Carlon PVC Pipe”.

 

Approved tapping saddles may be used in lieu of prefabricated T-Branches for use with Prestressed Concrete Cylinder Pipe and Ductile Iron Pipe.  The cost for each tapping saddle, including all work and equipment incidental to its placement shall be included in the price bid for Item 603 - 6” T-Branch of the size specified.

 

The Contractor may utilize an “Inserta Tee” connector, or equal, in lieu of prefabricated T-Branches for all conduits 21” diameter and greater, other than on Ductile Iron Pipe or Prestressed Concrete Cylinder Pipe.  The cost for each connector, including all work incidental to its placement, shall be included in the price bid for Item 603 – 6” T-Branch of the size specified.  The cost for six inch bends including all work, materials and equipment incidental to its placement shall be included in the price bid for Item 603 - 6” T-Branch of the size specified.

 

The price bid for these items shall be complete, including restoration.

 

 

603.019 (Ref. No. 9 through 12, 14 & 15) DEFLECTION TEST

 

A deflection test will be required on all main line P.V.C and C.C.F.P. sewers as specified in the City of Cincinnati Supplement to the State of Ohio, Department of Transportation, Construction and Material Specifications.  Maximum limit for vertical deflection shall be 5% of the pipe inside diameter.

 

 

603.029 (Ref. No. 24) VIDEO TAPING OF INSTALLED SEWERS

 

Contractor to furnish video taping of installed sewers meeting the requirements of Item 603.029 of the City Supplement to the State of Ohio (ODOT) Construction and Material specifications.

 

The Contractor is required to submit complete electronic worksheets and inspection reports to document the work that is performed and the condition of the sewer and the manholes.

 

To support the electronic submission of reports and worksheets, the Contractor must have the following minimum computer equipment:

 

·        Pentium II computer 300 MHZ, RAM 64 MB (preferably 128 MB), adequate hard drive space (min. 160 MB/year of data).

·        Snappy 4.0 Video Capture Hardware (incl. Software) (approx. $30)

Available at:      http://www.solutions4sure.com/

                        Search on keyword “snappy”

                        1-800-644-9866

 

·        Compact Flash Card Reader

·        2 Compact Flash Memory Cards 16 Meg.

·        RCA Video Adapter

 

Custom application software for completing the electronic submittals will be provided by MSD. MSD will also provide approximately 6-8 hours of training for each employee that will be inputting the data for the Contractor.

 

 

603.061 (Ref. No. 9 through 15) LEAKAGE TEST

 

All mainline conduits shall be subjected to a leakage check either by an infiltration or exfiltration test with water or by an air test. Water infiltration or exfiltration tests will only be allowed for conduits larger than thirty-six (36) inches in diameter. The infiltration test allowance, for conduits larger than thirty-six (36) inches in diameter, shall be 0.079 gallons per inch of the internal pipe diameter per 100 feet of conduit per hour. The exfiltration test allowance shall be the same as for infiltration except that an additional allowance of ten (10) percent shall be permitted over the basic allowance for each two (2) feet of head over a basic two (2) foot minimum.

 

All conduits thirty-six (36) inches and smaller shall be subjected to an air test.  This test shall be performed in accordance with the latest ASTM or UNI-BELL PVC Pipe Association requirements for each unique pipe material in effect at the time that bids are submitted.

 

The Contractor shall perform the leakage test at the Contractor’s expense, including the furnishing of all labor, materials, and appurtenances necessary for the performance of the leakage test.  The cost of the leakage test shall be included in the price bid for the appropriate 603 items.

 

Flow will be permitted through the newly constructed sewer, prior to testing requirements being met, on an as needed basis, as directed by the Engineer. 

 

The leakage test shall not be required if construction of the proposed sewer requires that an active lateral connection be made at time of installation of mainline sewer, due to removal of the existing mainline sewer or existing lateral.  All other testing, including deflection testing and video taping shall be required, which may require flows to be stopped or pumped until deflection test and video taping is complete.

 

 

603.08 (Ref. Nos. 9 through 18) BACKFILLING

 

Bank run gravel backfill above the "initial backfill" shall be required for Type "B" conduit and in the following locations:

 

A.        Where the trench parallels a road or street pavement and any part of the trench is within two feet of the edge of the pavement, bank run gravel backfill shall be used and shall extend to the pavement subgrade for the entire width of the trench.

 

B.                 Where the trench crosses a road or street pavement, bank run gravel backfill shall be used and shall extend two feet on each side of the pavement at pavement subgrade (and shall extend beyond that point to the top of the initial backfill over the pipe at the angle of repose for bank run gravel).

 

Compacted bank run gravel backfill above the “initial backfill” shall be required for all conduits and trenches under driveway pavements, when not within two feet of a road or street pavement. 

 

Controlled Density Fill shall meet or exceed the requirements as defined in the latest edition of the “Rules and Regulations of the Office of the County Engineer Governing Driveway Regulations and Pavement and/or Right-of-Way Opening Provisions for the Unincorporated Area of Hamilton County”, including addendums and attachments thereto.

 

JETTING

 

In lieu of compacting the bank run gravel backfill in 4” lifts, the bank run gravel backfill may be compacted by thoroughly jetting with water, provided satisfactory drainage and removal of the free water is provided.  The Contractor shall provide a two (2) year guarantee against settling of the trench area.

 

The Bank Run Gravel backfill shall be finally consolidated by thoroughly jetting with water.  Trenches over 14 feet in depth shall be consolidated by jetting in two equal layers.  For jetting, a hose not smaller than 1-1/2 inch diameter and a nozzle not smaller than 1 inch diameter and not shorter than 2/3 the depth of the trench carrying a water pressure of 40 pounds per square inch (psi) shall be inserted in a uniform pattern to obtain maximum consolidation.  After the final jetting of the trench, the backfill shall be left to settle and to permit drainage of impounded water. Typical jetting procedures shall include a water removal system at intervals not to exceed 500 lineal feet of trench.  After jetting is complete, the area around the jetting hole shall be filled and compacted by the use of the bucket on the equipment used for excavating.  Settled trench surfaces shall then be brought to grade by filling with Bank Run Gravel backfill and compacted to a density equal to that of the adjacent ground.

 

Water shall be removed by installing an opening in the manhole and connecting and installing a vertical six inch perforated pipe with filter paper adjacent to the manhole, or by connecting and installing a five to six foot length of perforated pipe with filter paper parallel to the proposed main line conduit.   If the vertical pipe method is used, the vertical pipe shall be filled with #57 stone after all water is removed.  If the horizontal pipe method is used, the horizontal pipe shall be plugged and sealed inside the manhole. For both methods, the manhole opening shall be plugged and sealed after jetting and water removal operations are completed.

 

The Contractor shall include the cost for the necessary backfill with the various 603 items.  No additional payment shall be made for the use of Controlled Density Fill when required by the jurisdictional agency, or when required due to unsupported trenches, over excavating, or the inability to properly compact the granular backfill in the trench, as defined herein.

 

 

SPECIAL BACKFILLING REQUIREMENTS

 

Backfill material for Type "C" and Type “G” Conduit shall consist of suitable soil or granular material and shall be free from rubbish, muck, or other unsuitable materials.

 

Stones and shale exceeding one-half  (1/2) cubic feet in volume shall not be used in the backfill, and stones and shale that are used shall be separated by at least six (6) inches of earth.

 

The backfill for Type “C” Conduit shall be finally consolidated by thoroughly jetting with water. Trenches over 14 feet in depth shall be consolidated by jetting in two (2) equal layers.  For jetting other than granular material, a hose not smaller than 1 –1/2 inches in diameter and nozzle not smaller than 1 inch in diameter and not shorter than 2/3 the depth of the trench carrying water at a minimum pressure of 40 pounds per square inch (psi) shall be inserted into the back fill in a uniform pattern in order to obtain maximum consolidation.  After the final jetting of the trench, the backfill shall be left to settle and to permit drainage of the impounded water.  Typical jetting procedure shall include a water removal system, either natural or mechanical, at intervals not to exceed 500 linear feet of trench.  Settled trench surfaces then shall be brought to grade by filling with approved fill material and compacting to a density equal to that of adjacent ground.

 

The Contractor shall include the cost for the necessary backfill with the various 603 items.  No additional payment shall be made for the use of Controlled Density Backfill when required by the jurisdictional agency or due to unsupported trenches, over excavating, or the inability to properly compact the granular backfill in the excavated trench.

 

 

604 ( Ref. No. 19) STANDARD TYPE “S” MANHOLES

 

This item shall be constructed in accordance with Standard Drawing Acc. No. 49037, except as otherwise noted on the plans and in the specifications. 

 

If PVC pipe is installed, the pre-cast manhole base shall be used in accordance with Standard Drawing Acc. No. 49056.

 

 

604 (Ref. No. 20) STANDARD TYPE “S” DROP MANHOLES

 

This item shall be constructed in accordance with Standard Drawing Acc. No. 49003 and 49037 except as otherwise noted on the plans and specifications.

 

 

604 (Ref. No. 21) STANDARD TYPE “P” STORM MANHOLES

 

This item shall be constructed in accordance with Standard Drawing Acc. No. 49001, except as otherwise noted on the plans and in the specifications.

 

All Standard Type “P” Manholes shall have grating lids in accordance with Acc. No. 49007.

 

 

604 (REF. No. 22) STANDARD SINGLE GUTTER INLETS

 

This item shall be constructed in accordance with Standard Drawing Acc. No. 49011, except as otherwise noted on the plans and in the specifications.

 

All Standard Single Gutter Inlets shall have grating lids in accordance with Acc. No. 49012.

 

 

604 (Ref. Nos. 19 & 20) MANHOLES AND CASTINGS

 

The Contractor shall furnish all castings for this project, including manhole frames and covers.  All manhole frames and covers shall be in accordance with Standard Drawing Acc. No. 49005.

The Contractor shall securely fasten the frame to the concrete portion of the manhole by means of four (4) ¾ inch stainless steel cinch anchors with five-inch long bolts. 

 

If PVC pipe is installed, the precast manhole base shall be used in accordance with Standard Drawing Acc. Nos. 49056 and 49004.

 

All costs for dewatering, as necessary, shall be included in the price bid for these items.

 

The cost for castings, cinch anchors, bolts and anchor holes, and all work incidental to their placement shall be included in the price bid for these items.

 

The Contractor shall include the cost to connect the pipe or pipes to the proposed manholes, including the cost of any pipe, materials, labor, excavation and restoration required, in the price bid for these items.

 

Butyl mastic seals shall be used at all manhole joints and at the concrete adjusting rings as shown on MSD Standard Drawing Acc. Nos. 49003, 49037 and 49049.

 

Whenever it is necessary to remove an existing manhole and/or pipe in order to construct a new manhole, the cost for removing the existing manhole and/or pipe, including the cost for disposing and transporting of materials or any additional excavation, restoration, or labor required, shall be included in the price bid for these items.

 

 

604 (Ref. No. 23) REMODEL BOTTOM OF EXISTING MANHOLE

 

This item shall be constructed in accordance with Standard Drawing Acc. No. 49004 and as directed by the Engineer.

 

 

604 (Ref. No. 19 & 20) MANHOLE VACUUM TEST

 

The Contractor shall test all manholes for leakage by means of vacuum testing.  The vacuum testing shall not be performed until after the manholes are set to final grade and the manhole castings are bolted down.  All lift holes shall be plugged.  Any other openings, such as pressure relief valves, shall be temporarily plugged to allow the vacuum tests.  All pipes entering the manhole shall be plugged and care shall be taken to securely brace the plugs from being drawn into the manhole.  The vacuum equipment test head shall be placed in the opening of the casting only and the seal inflated in accordance with the manufacturer’s recommendations. 

 

Vacuum testing shall be in accordance with ASTM C1244.  A vacuum of ten inches of mercury (10” Hg) shall be drawn and the vacuum pump shut off.  With the valves closed, the time shall be measured for the vacuum to drop to nine inches of mercury (9” Hg).  The manhole shall pass if the time meets or exceeds the allowable times as calculated from ASTM C1244, or as approved by the Engineer.  All manhole repair and testing required because of the failure to meet the testing requirements shall be at the Contractor’s cost.  The cost of the manhole vacuum leakage test shall be included in the price bid for the various 604 items.

 

 

 

 

SPECIAL (Ref. No. 25) PERFORMANCE BOND

 

The Contractor shall include the cost of the Performance Bond in the Proposal.  The cost entered in the Proposal should not exceed one percent (1%)of the official bid price. 

 

This item shall be included for payment on the first partial estimate.

 

In the event the cost entered in the Proposal exceeds one percent (1%), the cost over one percent (1%) will be paid with the final payment.

 

 

FINAL PAYMENT

 

Before final payment is made to the Contractor, the Contractor may be required to submit to the Engineer a release, in writing, from all the property owners whose property has been used by the Contractor outside the limits of construction and/or right-of-way.