msdgc.org Construction Contracts

 

MSD Home | Construction Contracts | Upcoming Projects | Projects on Sale | Bid Results

 

Bid Results: 187 First Street Sewer Replacement

 

This project has been bid and the construction contract is being processed. For bidding/contract details or information on the contract status, please contact (contact information). For project-specific details, please contact the Project Manager at the number listed in the table below.

 

Bid Results

Project Name

187 First Street Sewer Replacement

Sewer No.

5821

CIP No.

2007-34

Bid Opened

09/11/2007

Project Type

Sanitary Sewer

Low Bidder

Rack & Ballauer Excavating Co.

Low Bid (Codes)

$36,070.00 (GG)

Estimate

$65,000.00

Contract Status

Contract Processing

Project Manager

Tony Yee, WWE @ (513) 244-5180

Time to Complete

3 months after contract award completed

 

Related Documents

Legal Notice

Detailed Provisions

Bid Items

Plan Holders List

Bid Booklet

Bid Tabulations

Prevailing Wages

 

 

Bidder Codes

Code

Contractor Type

G

General Contractor

P

Plumbing Contractor

H

HVAC (mechanical) Contractor

E

Electrical Contractor

C

Combined bid (G+H/P/E) Contractor

 

 

The msdgc.org site is a service of the MSD IT Group | Legal Notices | Page last updated October 2, 2007 by Mary Mount.