Trenchless Technology Sewer Rehabilitation, Phase V

Staff | General Information | Projects On Sale | Upcoming Projects | Bid Results

This project has been bid and the construction contract is being processed. For information on contract status, please contact Laura Brown of the Contracts Administration staff. For information on pending construction status, please contact the Project Manager at the number listed in the table below, or the Field Engineering Section's Construction Manager at (513) 244.1366.

PROJECT INFORMATION

Project

Sewer No.

CIP No.

Bid Opened

Project Type

Unofficial
Low Bidder

Unofficial
Low Bid
(Codes)

Estimate

 Contract Status

Time to Complete

Project Manager

Trenchless Technology Sewer Rehabilitation, Phase V

5461D

2004-01

02/22/2005

Sewer Rehabilitation

Insituform Technologies, Inc.

$1,202,314.00

(G)

$1,102,000.00

Processing

Contract

6 Months

Gene Weber, MSD WWC (513) 931-4519

UNOFFICIAL BID RESULTS

 Legal Notice

Specifications

Bid Items

The following table contains the preliminary, unofficial results of the bid opening for this project. Official results will be posted after verification of the bid documents.

Bidder

Amount

Insituform Technologies, Inc.

$1,202,314.00

American Water Services

$1,531,930.00

 Plans Holders List

BIDDER CODES

Code

Contractor Type

G

General Contractor

P

Plumbing Contractor

H

HVOC (mechanical) Contractor

E

Electrical Contractor

C

Combined bid (G+H/P/E) Contractor