Bid Results: Mill Creek WWTP  Liquid Treatment Process Improvements Phase 2 Coarse Screen Replacement - Contract 65

 

This project has been bid and the construction contract is being processed. For bidding/contract details or information on the contract status, please contact Anna Bennett of Contract Administration at (513) 557-7122. For project-specific details, please contact the Project Manager at the number listed in the table below.

 

Bid Results

Project Name

Mill Creek WWTP  Liquid Treatment Process Improvements Phase 2 Coarse Screen Replacement - Contract 65

Sewer No.

4910

CIP No.

2004-16

Bid Opened

2/28/2006

Project Type

Facilities Improvement

Low Bidder

Reynolds Incorporated

Low Bid (Codes)

$2,352,000.00 (G)

Estimate

$3,000,000.00

Contract Status

Contract Processing

Project Manager

Greg Doherty, MSD @ 244-1388

Time to Complete

Fifteen (15)  months after contract award completed

 

Related Documents

 

 

Bidder Codes

Code

Contractor Type

G

General Contractor

P

Plumbing Contractor

H

HVAC (mechanical) Contractor

E

Electrical Contractor

C

Combined bid (G+H/P/E) Contractor

 

 

The msdgc.org site is a service of the MSD IT Group | Legal Notices | Page last updated March 7, 2006, by Anna Bennett.