Bid Results: Pleasant Run Drainage Basin Facilities Upgrade  Phase 2 - Force Main Improvements

 

This project has been bid and the construction contract is being processed. For bidding/contract details or information on the contract status, please contact Anna Bennett of Contract Administration at (513) 557-7122. For project-specific details, please contact the Project Manager at the number listed in the table below.

 

Bid Results

Project Name

Pleasant Run Drainage Basin Facilities Upgrade  Phase 2 - Force Main Improvements

Sewer No.

4863

CIP No.

97-112

Bid Opened

1/31/2006

Project Type

Sanitary Sewer

Low Bidder

Larry Smith Contractors, Inc.

Low Bid (Codes)

$1,547,452.00 (G)

Estimate

$1,781,000.00

Contract Status

Contract Processing

Project Manager

William Lutz, MSD WWE @ (513) 244-5102

Time to Complete

12 months after contract award completed

 

Related Documents

 

Bidder Codes

Code

Contractor Type

G

General Contractor

P

Plumbing Contractor

H

HVAC (mechanical) Contractor

E

Electrical Contractor

C

Combined bid (G+H/P/E) Contractor

 

 

The msdgc.org site is a service of the MSD IT Group | Legal Notices | Page last updated February 3, 2006, by Anna Bennett.