Contract Awarded: Carr Street Access Rehab

 

This project has been awarded.  For bidding/contract details, please contact the Contract Administrator listed in the table below. For project-specific details, please contact the Project Manager at the number listed in the table below.

 

Bid Results

Project Name

Carr Street Access Rehab

Project ID

10240415

On Sale Date

9/16/2014

Bid Opened

10/07/2014

Project Type

Manhole Rehabilitation

Awarded

Adleta Construction

Contract Status

Awarded

Project Manager

Wes Wimmer  @ 513-557-7129

Contract Administrator

Mark Menkhaus, Jr. @ 513-244-1383

Date For Substantial Completion

150 Days After Notice to Proceed

Date For Final Completion

30 Days After Date for Substantial Completion

 

Related Documents

Legal Notice

Detailed Provisions

Plan Holders List

Bid Booklet

Bid Tabulations

Prevailing Wages

 