MSD Home | Construction Contracts | Upcoming Projects | Projects on Sale | Bid Results
This project has been bid and the construction contract is being processed. For bidding/contract details or information on the contract status, please contact the Contract Administrator listed in the table below. For project-specific details, please contact the Project Manager at the number listed in the table below.
Bid Results
|
Project Name |
Hengehold 4th and Yates 3rd Pump Stations Elimination |
|
Sewer No. |
4995 |
|
CIP No. |
2005-11 |
|
Bid Opened |
12/04/2007 |
|
Project Type |
Sanitary Sewer |
|
Low Bidder |
Rack & Ballauer Excavating Company |
|
Low Bid (Codes) |
$414,072.00 (G) |
|
Legislated Amount |
$737,500.00 |
|
Contract Status |
Contract Processing |
|
Project Manager |
Rick Anderschat, WWE @ (513) 244-1396 |
|
Contract
Administrator |
Mary Mount, (513) 244-1383 |
|
Time to Complete |
Six (6) months after contract award |
|
Code |
Contractor Type |
|
G |
General Contractor |
|
P |
Plumbing Contractor |
|
H |
HVAC (mechanical) Contractor |
|
E |
Electrical Contractor |
|
C |
Combined bid (G+H/P/E) Contractor |
The msdgc.org site is a service of the MSD IT Group | Legal Notices | Page last updated January 11, 2008, by Mary Mount.