logo_cityofcinti_msd_390      msdgc.org Construction Contracts

 

MSD Home | Construction Contracts | Upcoming Projects | Projects on Sale | Bid Results

 

Contract Awarded: Muddy Creek WWTP Grit Replacement (Re-bid)

 

This project has been awarded.  For bidding/contract details, please contact the Contract Administrator

listed in the table below.  For project-specific details, please contact the Project Manager at the number listed in the table below.

 

Bid Results

Project Name

Muddy Creek WWTP Grit Replacement (Re-bid)

Project ID

10131240_R

On Sale Date

10/23/2014

Bid Opened

11/13/2014

Project Type

WWTP

Awarded

Dugan & Meyers Construction Co.

Contract Status

Awarded

Project Manager

Tony Yee  @ 513-244-5180

Contract Administrator

Mark Menkhaus, Jr., 513-244-1383

Date For Substantial Completion

485 Days After Notice to Proceed

Date For Final Completion

90 Days After Date for Substantial Completion

 

Related Documents

Legal Notice

Detailed Provisions II

Detailed Provisions III

Plan Holders List

Bid Booklet

Bid Tabulations

Addendum 1

Addendum 2

Addendum 3

Prevailing Wages

 

The msdgc.org site is a service of the MSD IT Group | Legal Notices | Page last updated February 20, 2015, by Mark Menkhaus, Jr..